- The court found that the municipality’s claim for the transfer of land constituted a “debt” under the Prescription Act and was therefore subject to prescription.
- The municipality’s right to reclaim the property arose in 2009, but legal action was only taken in 2020, more than 11 years later.
- The court ruled that the claim had prescribed after three years and ordered the Municipality to pay the costs of the application.
A municipality’s attempt to reclaim land it sold more than a decade ago has failed after the High Court in Mahikeng ruled that it waited too long to act, allowing the claim to expire by law.
The dispute between Mahikeng Local Municipality and Mike Ishmael Binazir centred on a property sale dating back to 2005. Binazir had purchased land from the municipality on the clear condition that he would build on it within two years.
When he failed to do so, the municipality became entitled to demand the return of the property, but it only moved to enforce that right in 2020, more than 11 years after the deadline had passed.
Judge President RD Hendricks made it clear that the delay was fatal to the municipality’s case, finding that its claim had prescribed in terms of the Prescription Act.
Background and the parties
Mahikeng sold a property to Binazir in August 2005 for just over R12,000. The transfer was completed in April 2007, at which point Binazir became the registered owner.
The agreement required Binazir to erect a structure on the property within two years of transfer. Notably, this obligation was not merely contractual. It was also recorded as a condition in the title deed, giving it additional legal weight.
Judge Hendricks explained, “The deed of sale imposed a material condition upon the defendant… to erect… a structure on the property… within a period of two years from the date of registration of transfer.”
When Binazir failed to build within the required period, which expired on 15 April 2009, the municipality became entitled to invoke a reversionary clause allowing it to reclaim the property upon refunding the purchase price.
The municipality’s claim and Binazir’s defence
Despite the breach having occurred in 2009, the municipality only instituted legal proceedings in December 2020, seeking to compel Binazir to transfer the property back.
Binazir raised a special plea of prescription, arguing that the municipality’s claim had expired after three years in terms of section 11(d) of the Prescription Act.
The municipality pushed back, contending that its right to reclaim the property was not a “debt” but rather a discretionary contractual right, an option that could be exercised at any time, or at the very least within a reasonable period.
Judge Hendricks rejected this characterisation, emphasising that the nature of the claim must be assessed in substance rather than form.
The court’s reasoning on prescription
The court found that a claim to compel the transfer of immovable property constitutes a legal obligation and therefore qualifies as a “debt” under the Prescription Act.
Judge Hendricks stated, “That claim gives rise to an obligation on the part of the defendant to effect the transfer of immovable property… such an obligation constitutes a ‘debt’ for purposes of the Prescription Act.”
The court also relied on established precedent, including decisions confirming that reversionary clauses in property agreements create enforceable obligations that are subject to prescription.
Importantly, the court held that the municipality’s right became enforceable the moment the breach occurred in April 2009, giving it a complete cause of action from that point forward.
Judge Hendricks explained, “Upon the defendant’s failure to comply… the municipality became entitled to enforce the reversionary clause… the debt… was therefore due.”
Because the claim qualified as a debt, it was subject to a three-year prescription period. The court rejected the municipality’s argument that a longer 15-year period applied, or that general notions of reasonableness could extend the time to act.
In firm terms, Judge Hendricks stated, “The Act provides a comprehensive and exhaustive regime… It does not allow for a parallel enquiry based on general notions of reasonableness.”
A delay that proved decisive
The court found no evidence that the prescription had been interrupted or suspended. As a result, the municipality’s claim was prescribed in April 2012, exactly three years after the breach. By the time legal proceedings were finally launched in 2020, the claim had long since expired.
Judge Hendricks concluded, “The municipality’s claim became due on 15 April 2009 and was extinguished by prescription on 15 April 2012.” The court further noted that the matter closely mirrored previous litigation involving similar issues.
Final order
The court upheld Binazir’s special plea of prescription and dismissed the municipality’s claim. Judge Hendricks ordered, “The Defendant’s special plea of extinctive prescription… is upheld.”
The municipality was also ordered to pay the costs of the application.
Get your news on the go. Clickhereto follow the Conviction WhatsApp channel.


